Miller Street project close to being finished

Printer-friendly versionPrinter-friendly version

New Haven, Mo – Friday afternoon we spoke with Public Works Director, Julius Gatzemeyer about progress on phase one of the Miller Street project.

Gatzemeyer said, “Work on the gas and water lines have been completed as well as the sewer and storm drains.”

The project began back in April and according to the contract signed with KJU Inc., phase one should be completed sometime this month unless weather would cause any type of delays.

Gatzemeyer said, “Right now they are working on curbing and guttering as well as residents’ driveways.  Once completed they will proceed with paving Miller [Street] and be finished with the first phase.”

The second phase is scheduled for this summer, beginning towards the end of June with completion anticipated by early September.

Storm drain installed on the right side of Miller Street.