Olive Street Bridge making good progress -- Time line of photos

Printer-friendly versionPrinter-friendly version

Photos by Kyle Quick
Pictured above is what has been completed as of Oct. 11.

During last night's board of aldermen meeting, Steve Roth said that the contractor is making good progress on the Olive Street Bridge project and it could be open to traffic as early as next week.

The contractor is hoping to complete curb and gutter and asphalt paving before the end of the construction season.  However, Roth pointed out that in the contract it is not required for asphalt paving to be completed before winter. Roth said, "This would not be optimum but would at least be open to two-way traffic.

Below are photos from when demolition began to present.